Click An Image To Enlarge:

Flood Floor Construction:

The quality of a flood floor starts in the very first stages of construction. Zwart Systems works very closely with Al Brower of Tradewind Construction. A Zwart Systems consultant will begin with the customer to determine what type of floor is right for them. After this decision is made and the quote is accepted Zwart will look after the scheduling of the project and provide a complete project for the customer.

  1. It all begins with taking elevation shots.
  2. Remove or add soil as required.
  3. Then some excavation for the mainlines and spur lines takes place.
  4. Next a little laser grading to make the base exactly mirrored to what the finished concrete should be.
  5. Lay down some wire mesh and rebar.
  6. Tie down the heat tubing.
  7. Time to pour an even contoured 4” of concrete with a screed. (5” on the main walkway).
  8. Drill some holes and rubber barrier.
  9. Add water and plants.

If these 9 steps look easy, its because that’s how we make it look. A lot of engineering and planning goes into each project. If you need some budget numbers or would like to discuss if this system is right for you give us a call. We are always happy to chat about a project and if it fits your business plan we will make a site visit with all the necessary people to give you an accurate quote.